OpenOct 16, 2026
Due by November 22, 2026
•Last updated Deliverable: a stable sketch API and CAN wire format — after this, a breaking change means 2.0. Released before Phase 6 panel work (Right_Navigation).
Needs: "Base boards Rev 2 + soak test rig" and Firmware v0.2.0 (the PDU is on the soak bus)
Window (blackout Oct 30–Nov 6) — decided at the Oct 21 go/no-go, on whether the Rev 0.2.0 boards have arrived:
- Path A: soak Oct 26–29 · fixes / re-soak Nov 7–13 · tag Nov 13
- Path B: soak Nov 9–15 · fixes / re-soak Nov 16–21 · tag by Nov 22 (due date)
Work order
- #295 — API + wire-format freeze review and compatibility policy (can start as soon as v0.2.0's frame is defined)
- #304 — release bundle (sample sketches + prebuilt SimGateway / PanelBridge binaries)
- #290 — first soak (Path A Oct 26–29 / Path B Nov 9–15)
- Fixes / re-soak
- Tag v1.0.0
50% complete